Difference in MOPD scheduling and Sales order scheduling
Summary:
Item A is
Manufactured in - ORG A (Manufacturing lead time = 45 days)
Ordered and shipped from distribution center - ORG B (Transit time between org A and org B = 4 days)
Sourcing rule 1 - Make in Org A and assigned to Org A
Sourcing rule 2 - Transfer from Org A and assigned to Org B
Create an order in Org B and system schedules with just 4 days lead time and is not considering the manufacturing lead time 45 days.
However, when the same details are entered in MOPD, it is calculating 45+4 and showing 49 days delay for order from Org B
Below is MOPD screenshot where item is ordered from Org A and system considering manufacturing lead time of 45 days as delay