Difference in MOPD scheduling and Sales order scheduling

Summary:

Item A is

Manufactured in - ORG A (Manufacturing lead time = 45 days)

Ordered and shipped from distribution center - ORG B (Transit time between org A and org B = 4 days)

Sourcing rule 1 - Make in Org A and assigned to Org A

Sourcing rule 2 - Transfer from Org A and assigned to Org B


Create an order in Org B and system schedules with just 4 days lead time and is not considering the manufacturing lead time 45 days.

However, when the same details are entered in MOPD, it is calculating 45+4 and showing 49 days delay for order from Org B


Below is MOPD screenshot where item is ordered from Org A and system considering manufacturing lead time of 45 days as delay