Rework Work Orders creating extra demand instead of using the same on hand at Rework subinv
Summary:
Planning is seeing that the projected available supply in org is doubled because the inventory exists in On Hand AND the rework WO is indicating that more inventory will be created. The plan does not consider that the original inventory will be consumed to complete the rework work order (unless the work order is released and then the inventory disappears from On Hand).
Content (please ensure you mask any confidential information):
Planning is seeing that the projected available supply in org is doubled because the inventory exists in On Hand AND the rework WO is indicating that more inventory will be created. The plan does not consider that the original inventory will be consumed to complete the rework work order (unless the work order is released and then the inventory disappears from On Hand).