Control Budget is using a different calendar than expected
Hi, hope you can help me in this.
I created Project #34, which uses a Financial Plan Type and Project Plan Type where "Accounting Calendar" is parametrized as the option for Budget Generations, we're using the same accounting calendar for Projects and Financials.
I did the Budget maintenance for periods 9-23, 10-23, 11-23, 12-23, 01-24, 02-24, 03-24, 04-24, 05-24, 06-24 and 07-24, where there are funds from 01-24 to 04-24 for Labor expenditure, 100 hours, 10.000.000 CRC, after this we set this budget as Baseline, by this moment on "Manage Project Buget" we have "Version 2" as "Current and Original Baseline".
Then we were doing some testing for creating labor cost from ADFdi, we uploaded the template with 8 hours, 62.000 CRC for a resource of the same expenditure type "Labor", and it fails Budgetary Control Validatios for "insuficient funds".