Warning in PR for Project
Summary:
Hi All
Does SSPR provide a warning when a PR orders an item for Project needs and calculates the purchase lead time with the Project Task start date?
For example, we have a project to build a bridge. We need paint to color the bridge in the next 14 days. To buy paint until it arrives in hand, it takes 17 days. Can Oracle provide warnings when submitting PR? This case is also included when ordering service.
Please help us.
Thank you
Regards
Aji