Shift Schedules changed in plant parameters of maint org does not generate forecasting
Summary:
We have shift schedule marked as monday to friday timing 08:00am to 05:00pm and under standard operation resource assignment we have marked scheduled as YES so when ever we are creating any Corrective or Preventive work order this follows the shift pattern and does not generate any work orders on sat and sun this is as expected behaviour of system.
But as of new business requirement they want to change this shift schedule from Monday to Sunday timing 08:00am to 10pm we have created this shift schedule and assign this to plant parameters since we only have one work center per maintenance org so we assigned this to plant parameters now as per new schedule system is generating work order as per new schedule also maintenance forecasitng for preventive maintenance is generating on the basis of new shift pattern but when we again change the shift schedule again to monday to friday timing 08:00am to 06:00pm system is not generating