Deliverable due date for repeating deliverable
Summary:
We have a contract with start date 01/01/2020 and end date 30/03/2025. Then we create a repeating deliverable for every one year. Initially, the deliverable generate correctly like below
01/01/2020
01/01/2021
01/01/2022
01/01/2023
01/01/2024
01/01/2025
When the contract come to end, we decide to extend the contract for another one year by changing the end date to 30/03/2026. We expect another deliverable will be generated on 01/01/2026. But instead, the system generate the deliverable on 01/04/2025. It looks system is generated the deliverable for next month based on the last end date. And it is not following the original deliverable schedule. Is that something we setup wrongly or not.