Is there a way to do a bulk update of PPM Project and Tasks?
Summary:
Hi,
As part of Fusion PPM implementation for our client, we have a requirement to create an integration which inbounds Projects, Project Tasks, and Project Classification into Fusion PPM Cloud. Our client has 10000+ projects to be imported into Oracle PPM cloud every hour and these includes creation & updates. Hence we are looking for an approach which can be used to do a batch update of projects and tasks.
Content (required):
If we understood correctly from Oracle Note Doc ID 2241161.1 , project updates are not supported using FBDI. Is there any workaround which can be used to Bulk update projects and tasks except REST API?