Project Budget Vs Requisition
Summary:
Project Budget Vs Requisition
Content (please ensure you mask any confidential information):
Project Budget = 50,000,000
Project Actual Cost = 35,000,000
Project Committed Cost = 5,000,000
Total Project Cost = 35,000,000 + 5,000,000 = $40,000,000
Available amount to spend is 10,000,000.
Why am I getting a Funds Check error when creating a requisition from the said project budget for 4,000,000? When I check the Funds Check Budget from requisition check funds screen, I am seeing Requested amount $4,000,000 and available amount 2,000,000.
There should be 10M available, now am seeing only 2M when creating a requisition.
Why is the other 8M not available?
Where can I go to see what consume or make up the 8M? Its not reflected under Project Actual or Committed Cost.