For more information, please refer to this announcement explaining best practices for getting answers to questions.
How do I get a checklist task assigned according to the setup?
Summary:
The checklist tasks are not being assigned to the appropriate performer.
Content (required):
Hello,
As per the attached screenshots, I have 3 tasks setup for my checklist.
Task 1 - performer is the initiator of the task
Task 2 - performer is the AOR - Union Representative
Task 3 - performer is the AOR - Contingent Representative.
For task 1, the line manager is initiating the task. Once they have completed their task, Task 2 is being assigned to the line manager again, not the AOR. Then, when task 2 is completed, Task 3 is being assigned again to the line manager. What I have done wrong in the configuration that the tasks keep getting assigned to the line manager/initiator?